摘要:2023上半年系統(tǒng)規(guī)劃與管理師上午考試已結(jié)束,為方便考生考后估分,希賽小編整理了網(wǎng)友回憶版2023上半年系統(tǒng)規(guī)劃與管理師上午真題答案(71-75),希望對考生考后估分有幫助。
很多考生關(guān)注2023上半年系統(tǒng)規(guī)劃與管理師上午真題答案,希賽小編為大家整理了網(wǎng)友回憶版2023上半年系統(tǒng)規(guī)劃與管理師上午真題(71-75),完整版真題可在本文文首或文末下載。答案解析請考生關(guān)注希賽真題公開課。
71、
Any one or any group of activities utilizing resources to transfer input into output can be viewed as a( ).
A、system
B、structure
C、procedure
D、process
72、
The process control charts are used( ).
A、to graph what typically focuses on the prevention of a problem
B、to detect the problem
C、to reject the problem
D、to determine the acceptability of the sample
73、
The IT service manager has learned that a software can improve the efficiency of current and future project tasks. Because the software is fresh to the Company. The engineer is not familiar with the software. The IT service manager decides to send the highest level engineer to attend the external training course. The project manager uses( )risk strategies.
A、mitigation
B、enhancement
C、development
D、sharing
74、
( )is closet to Deming's definition of Quality.
A、Conformance to requirements
B、Fitness for use
C、Continuous improvement of products and services
D、Customer focus
75、
The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternative new manager, the team is opposed to the comments from the new manager. The team is at( )development stages.
A、Forming
B、Storming
C、Norming
D、Performing
軟考科目怎么選?非計算機專業(yè)考哪個好?微信掃碼下方二維碼找答案?。?!
熱門:系統(tǒng)集成項目管理工程師備考 | 2025年軟考報名時間及入口 | 25上半年軟考準考證打印時間
推薦:系統(tǒng)規(guī)劃與管理師網(wǎng)絡課堂 |系統(tǒng)架構(gòu)設計師網(wǎng)絡課程 | 工信部信創(chuàng)認證培訓
活動:信息系統(tǒng)項目管理師學習包 | 系統(tǒng)架構(gòu)設計師學習包 | PMP續(xù)證 | 4月軟考??即筚?/a>
備考:章節(jié)練習+真題 | 軟考備考學習資料 | 軟考免費課程 | 軟考模擬考試
課程:論文專題講解 | 系統(tǒng)規(guī)劃與管理師報考指南 | 信息系統(tǒng)管理工程師報考指南 | PMP課程
軟考備考資料免費領(lǐng)取
去領(lǐng)取