試題71
Retail firms analyze consumer sales trends and user preferences through internet user data.This belongs to(  )application area
A.big data
B.cloud computing
C.internet of things
D.artificial intelligence
試題72
In the following cloud computing technology architecture,(  )represented by number 3

試題71Retail firms analyze consumer sales trends and user preferences through internet user data.This belongs to()application areaA.big dataB.cloud computingC.internet of thingsD.artificial intelligence試題72In the following cloud computing technology architecture,()represented by number 3A.PaaSB.SaaSC.IaaSD.cloud platform interface試題73The seven basic qua1i ty too1s are used wi thin in the context of the PDCA Cycle to solve qua1ity-related prob1ems. These too1s are used in()in the fo11owing processesA.p1an qua1ity namagementB.perform quality assuranceC.erform quality contro1D.perform quality improvement試題74()is the process of implementing risk response plans,tracking identified risks,moni toring residual risk, ,identifying new risk ,and evaluating risk processeffectivenessthroughout the project.A.Identify risksB.Contro1 risksC.Plan risk responsesD.P1an risk management試題75()is the approved version of the time-phased project budget ,xcluding any management reserves ,which can only be changed through formal change control preceduresandis usedas a basis for comparison to actua1 results.A.The contro1 accountsB.Funding requiremengC.The cost estimatesD.The cost baseline


A.PaaS
B.SaaS
C.IaaS
D.cloud platform interface
試題73
The seven basic qua1i ty too1s are used wi thin in the context of the PDCA Cycle to solve qua1ity-related prob1ems. These too1s are used in(  )in the fo11owing processes
A.p1an qua1ity namagement
B.perform quality assurance
C.erform quality contro1
D.perform quality improvement
試題74
(  )is the process of implementing risk response plans,tracking identified risks,moni toring residual risk, ,identifying new risk ,and evaluating risk process
effectiveness  throughout the project.
A.Identify risks
B.Contro1 risks
C.Plan risk responses
D.P1an risk management
試題75
(  )is the approved version of the time-phased project budget ,xcluding any management reserves ,which can only be changed through formal change control precedures  and  is used  as a basis for comparison to actua1 results.
A.The contro1 accounts
B.Funding requiremeng
C.The cost estimates
D.The cost baseline


返回目錄:2017下半年系統(tǒng)集成項(xiàng)目管理工程師考試上午真題匯總

點(diǎn)擊查看:2017下半年軟考真題參考答案+解析

在線(xiàn)估分:2017下半年系統(tǒng)集成項(xiàng)目管理工程師上午真題答案和解析